Timeframe: 18 Weeks
340m2
Specification
- Excavation on an area approx 315m²
- Placement and consolidation of approx 150mm of type 1 mot over area
- Supply and lay 90m² of Marshalls Granite eclipse
- Supply and lay Everedge Halesin or similar
- Lay 100mm of c35 concrete over 90m² and once cured apply 90m² of resin bonded gravel
- Supply and install 120m² of 32mm pile artificial turf
- Supply 3 x recessed manhole covers
- Supply and install 35m of Multiline Sealing V100s Aco drainage
- Demolish existing ventilation hatches to below FFL
- Supply and install all required ducting for lighting around garden including
- Cast 8x concrete plinths to a size of 0.7m x 0.7m x 0.7m
- Supply and placement of 1 x maidenhair tree (Ginkgo Biloba)
- Clearance of shrubbery and trees
- Excavate 5 x drain runs as marked in drawing
- All Excavations to run from Manhole 2 as far back as is necessary/possible
- Old drainage to be removed and replaced with plastic pipe
- Drainage to be laid on a bed of pipe bedding and topped with pipe bedding
Our customer contacted us with a restricted time frame in which the work had to be carried out due to completing being mandatory before the opening of the park. Due to the time of year and the British weather not being on side and working around other contractors this could have become a struggle. However, all teams set to work and the target was achieved with a very happy customer on completion.