Beeches Golf
Location: Knutsford, Cheshire.
136m2 of resin in Golden Pea
Timeframe: 3 Days
136m2
Specification
- Install aluminum edging supplied by customer
- Supply and install 136m2 of resin in Golden Pea at 18mm thickness on top of tarmac base
Upon being awarded with this installation it was asked that we install the aluminum rail around the perimeter of each section of pathway, this then added some extra time to our work which then meant we didn’t meet the original time frame given. Our customer was made up with the work carried out and would ask for certain areas to be tweaked, in which we did. As we could only pour sections at a time due to other contractors working around us, we kept a small team on this installation to keep numbers on site down. Another happy client for Terrabuild!
Timelapse Progress Video